Remodeling the Master Bath Week 13 & 14

Well, this is beginning to get old. The glass shower door that was supposed to be ready for Tuesday, was not. I finally got some news on what the problem may be. The fabricator has been having problems getting the tempered glass from the supplier of the proper quality. That has been delaying not just … Continue reading Remodeling the Master Bath Week 13 & 14

Remodeling the Master Bath Week 12

We were really hoping this would be the last week of the renovation. Monday the electricians showed up and got almost all their work done. All the lights are in, the new switches and outlets installed and the covers put on. Third room light and over-tub light installed Vent/Vent light installed Vanity lights and outlets … Continue reading Remodeling the Master Bath Week 12

Remodeling the Master Bath Week 11

Week 11 didn't start until Wednesday but got off to a good start with primer going on the walls and the first coat of the bathroom color getting applied. Thursday saw the finishing of the color painting with a second coat. The room is really starting to look good. All the masking was removed as … Continue reading Remodeling the Master Bath Week 11

Remodeling the Master Bath Week 10

Week 10 was rather slow. They did finish the lacquer work on all the cabinet frames. The cabinet doors and drawers were taken back to the shop to get finished. They then did more masking to get it ready for paint. They are going to paint a primer coat first before the color coat goes … Continue reading Remodeling the Master Bath Week 10

Remodeling the Master Bath Week 9

Sure enough on Monday the paint guys showed up and started masking the bathroom for the stain and paint to come. The next day they continued the masking and started staining some of the doors. They also installed a zipper door to help keep the stink at a minimum through the rest of the house. … Continue reading Remodeling the Master Bath Week 9